Project title: Design, supply, construction, installation and operation of drag conveyor
Employer: Iran's National Copper Industry Company
Place of execution: Shahrbabak copper smelter
Project start date: 04/06/1402
Project delivery date: 08/15/1402
Micro activities carried out in the project:
- Designing detailed plans, engineering and implementation of civil, electrical and mechanical projects
-Supply of material for the drag conveyor collection
- Construction, installation, testing and commissioning of the conveyor drag system